PROJECT DESCRIPTION

Distribution Automation Large Contract (DALCO)

Project Overview

Project Details

Total

1,619 substations

Years of Project Completion

2026-02-28

Project Owner

TNB

TNBES Role

Project Management

Project Performance

As of May 2021

Planned:

87%

Actual:

13%

13%

Completed

Scope of Work

  • Supply, Install, Test and Commission Distribution Automation (DA) facilities, including Plant Interfacing Work (PIW) for 11 kV Vacuum Circuit Breaker (VCB), and Motorised Ring Main Unit with Remote/Local (RMU R/L) substations, through ā€œIntegrated Inter-changeable DAā€.
  • Integrated Inter-changeable DA in a VCB substation & RMU R/L substations.
 

Take the first step towards greener energy services

Reach out to us and our representative will get in touch with you soon.

Integrated Facility Management (IFM)

At TNBES, we have competency in the Integrated Facility Management services. Facilities that are well-managed will enhance businesses by operate more effectively and efficiently. By managing and optimizing your buildingā€™s operation, this allows you to reduce your operational expenses and smoothen your daily operations that aligns with the Environmental, Social, and Governance (ESG) Goals. With a proper Planned Preventative Maintenance (PPM) execution, it can reduce the breakdown frequency of your facilities so that your business operation flows smoothly.