PROJECT DESCRIPTION

Melaka Substation Maintenance

Project Overview

Project Details

Total

1429 substations

Completion Date

September 20, 2023

Project Owner

TNB

TNBES Role

Operation & Maintenance

Project Performance

As of May 2021

Planned:

86%

Actual:

14%

14%

Completed

Scope of Work

A maintenance project for TNB Substation in the Melaka region, specifically in M1 subzone which covers Melaka Tengah, Jasin And Merlimau areas. The project covers electrical and civil maintenance works for all substations up to 11kV in M1 region.

  • Preventive Maintenance for substation
  • Routine & Visual Maintenance
  • Other Civil & Electrical Works
  • CBM defect equipment replacement
  • Substation Cable Laying (Repair of Defect Cable and Switchgear)
  • Additional work of cable laying in pipe (if required)
  • Cross Zone Work (if required)