PROJECT DESCRIPTION

Pos Lenjang Micro Hydro

Project Overview

Project Details

Total

4 Stations - 187kW

Completion Date

December 20, 2024

Project Owner

TNB

TNBES Role

EPCC Contractor

Project Performance

As of May 2021

Planned:

87%

Actual:

13%

13%

Completed

Scope of Work

  • Engineering, procurement, construction and commissioning (EPCC) of 4 Micro Hydro Systems.
  • Provide electricity supply infrastructure in 10 villages in Pos Lenjang.
  • Increase the electrical coverage in rural Pos Lenjang.
  • Help in elevating the socio-economic status of each villager in Pos Lenjang.
  • Raise Orang Asli’s awareness on micro hydro technology system.

Take the first step towards greener energy services