PROJECT DESCRIPTION

Renewable Energy Plant Rehabilitation Works

Project Overview

Project Details

Total

16 Mini Hydro Stations

Completion Date

December 20, 2019

Project Owner

TNB

TNBES Role

O&M Rehabilitation

Project Performance

As of May 2021

Planned:

100%

Actual:

100%

100%

Completed

Scope of Work

  • Improve access road to intake and power house.
  • Refurbish Penstock.
  • Refurbish nozzle assembly, turbine runner assembly, and electro-mechanical assembly.
  • Install new generator control board, DC battery charger and battery bank, and new internal electric circuit.

Take the first step towards greener energy services